Lesson 4 of 7
Check the timeline
3 min
See every revenue and cost line placed on the programme.
The "Timeline" tab is a read-only Gantt of the study's line items. It exists to catch timing mistakes — a cost that lands before the start date, or revenue that settles before practical completion.
- 1
Open the Timeline
Select "Timeline". Each revenue and cost line appears as a bar across the study's months, colour-coded by category, with revenue in its own colour.
- 2
Sanity-check the sequence
Look for lines that start too early, run past completion, or all land in one month because a timing field was left at its default.
- 3
Fix timing where it is set
Timing is edited on the line item itself in "Revenue & Costs" — the Timeline reflects it, it does not set it.
- 4
Understand why it matters